Nozzle Assy
Nozzle Assy InstallationConnecting Rod Big End Side Clearance Inspection
Measure connecting rod big end side clearance.
Insert a thickness gauge [A] between the big end and either
crank web to determine clearance.
Connecting Rod Big End Side Clearance
Standard: 0.13 0.38 mm
(0.0051 0.0150 in.)
Service Limit: 0.58 mm (0.023 in.)
If the clearance exceeds ...
Engine Vacuum Synchronization Inspection
NOTE
These procedures are explained on the assumption that
the intake and exhaust systems of the engine are in
good condition.
Situate the motorcycle so that it is vertical.
Remove:
Fuel Tank (see Fuel Tank Removal in the Fuel System
(DFI) chapter)
Air Cleaner Housing (see Air Cleaner ...
Idle Speed Control Valve Actuator Input Voltage Inspection
NOTE
Be sure the battery is fully charged.
Turn the ignition switch to OFF.
Disconnect the idle speed control valve actuator connector
and connect a suitable measuring leads [A] between
these connectors as shown in the figure.
Main Harness [B]
Idle Speed Control Valve Actua ...