Nozzle Assy
Nozzle Assy InstallationLights and Switches Operation Inspection
First Step
Set the gear position in the neutral position.
Turn the ignition switch to ON.
The following lights should go on according to below table.
If the following light does not go on, inspect the meter
unit (see Meter Unit Inspection in the Electrical System
chapter).
...
Steering Damper Installation
Install the following parts as shown in the figure.
Collar [A]
Washer (t = 3.5 mm, 0.14 in.) [B]
Steering Damper [C] (
ZX1000JC/KC)
Electronic Steering Damper [D] (ZX1000JD/KD)
Washer (t = 1.2 mm, 0.05 in.) [E]
Apply a non-permanent locking agent to the threads of
the steering ...
Main Throttle Sensor Output Voltage Inspection
Measure the output voltage at the main throttle sensor in
the same way as input voltage inspection, note the following.
Disconnect the main throttle sensor connector and connect
the setting adapter [A] between these connectors.
Special Tool - Throttle Sensor Setting Adapter: 57001
-15 ...