Throttle Body Assy Assembly
Before assembling, blow away dirt or dust from the throttle body and delivery pipe assy by applying compressed air. Replace the O-rings [A] of the joint pipe [B] with new ones. Apply engine o ...

Nozzle Assy Removal
Remove the fuel tank (see Fuel Tank Removal). Disconnect the secondary fuel hose [A] from the delivery pipe assy of the nozzle assy [B] (see Fuel Hose Replacement in the Periodic Maintenance ...

Other materials:

DFI System Wiring Diagram
Part Names 1. Air Intake Solenoid Valve (Other than US, CA and CAL Models) 2. Front Wheel Rotation Sensor 3. Engine Stop Switch 4. Starter Button 5. Air Switching Valve 6. Stick Coil #1, #2, #3, #4 7. Spark Plugs 8. Intake Air Temperature Sensor 9. Crankshaft Sensor 10. Secondary Fuel ...

Amplifier Input Voltage Inspection
NOTE Be sure the battery is fully charged. Turn the ignition switch to OFF. Remove the upper fairing (see Upper Fairing Removal in the Frame chapter). Do not disconnect the connectors. Connect a digital meter to the amplifier connector [A] with needle adapter set. Special To ...

Rear Shock Absorber Installation
Replace the rear shock absorber nuts and tie-rod nuts with new ones. Tighten: Torque - Rear Shock Absorber Nuts: 34 N·m (3.5 kgf·m, 25 ft·lb) Tie-Rod Nuts: 34 N·m (3.5 kgf·m, 25 ft·lb) When installing the rear shock absorber bracket [A], install it so that the recess side [B] ...